April 14, 2015 All Nine Buildings Underway
The Valley Crossing Condos are in full swing with sales started and all nine buildings underway. Let’s hope the weather cooperates so that we can get outside work done in anticipation of possession dates.
Building E – Our Show Suites are open daily & we’re looking forward to seeing landscaping coming soon!
Building G – Final touch ups are happening and we’ll be having homeowners moving in by June.
Building I – Cabinets are being installed. Flooring, finishes, & painting underway.
Building F – Building is wrapped & ready for siding.
Building H – Framing is well underway with roofing & shingles happening soon!
Building A – We’re ready for the slab floor & for framing to start.
Building B – Foundation is in progress.
Building C – Footings are in.
Building D – Excavation complete and ready for footings to go in.